Thursday 15 September 2011

Bushehr Nuclear Power Plant

Bushehr Nuclear Power Plant,  نیروگاه اتمی بوشهر, is a nuclear power plant in Iran 17 kilometres (11 mi) southeast of the city of Bushehr, between the fishing villages of Halileh and Bandargeh along the Persian Gulf. The plant is located at the junction of three tectonic plates.
Construction of the plant was started in 1975 by German companies, but the work was stopped in 1979 after the Islamic revolution of Iran. A contract for finishing the plant was signed between Iran and the Russian Ministry for Atomic Energy in 1995, with Russia's Atomstroyexport named as the main contractor. The work was delayed several years by technical and financial challenges as well as by political pressure from the West. After the construction almost ground to a halt in 2007, a renewed agreement was reached in which the Iranians promised to compensate for rising costs and inflation after completion of the plant. Delivery of nuclear fuel started the same year. The plant started adding electricity to the national grid on 3 September 2011, and was officially opened in a ceremony on 12 September, attended by Russian Energy Minister Sergei Shmatko and head of the Rosatom Sergei Kiriyenko.
The project is considered unique in terms of its technology, the political environment and the challenging physical climate. It is the first civilian nuclear power plant built in the Middle East.



History


Inception


The facility was the idea of the Shah Mohammad Reza Pahlavi. He wanted a national electrical grid powered by nuclear power plants. Bushehr would be the first plant, and would supply energy to the inland city of Shiraz. In August 1974, the Shah said, "Petroleum is a noble material, much too valuable to burn... We envision producing, as soon as possible, 23,000 megawatts (MW) of electricity using nuclear plants".






Construction by German companies


In 1975, German Kraftwerk Union AG, a joint venture of Siemens AG and AEG Telefunken, signed a contract worth US$4–6 billion to build the pressurized water reactor nuclear power plant. The work was begun in the same year. The two 1,196 MWe reactors, subcontracted to ThyssenKrupp AG, were based on the Convoy design and identical with the second reactor unit of the German Biblis Nuclear Power Plant. The first reactor was to be finished by 1980 and the second one by 1981.
Kraftwerk Union was eager to work with the Iranian government because, as its spokesman said in 1976, "To fully exploit our nuclear power plant capacity, we have to land at least three contracts a year for delivery abroad. The market here is about saturated, and the United States has cornered most of the rest of Europe, so we have to concentrate on the third world."
Kraftwerk Union fully withdrew from the Bushehr nuclear project in July 1979, after work stopped in January 1979, with one reactor 50% complete, and the other reactor 85% complete. They said they based their action on Iran's non-payment of $450 million in overdue payments. The company had received $2.5 billion of the total contract. Their cancellation came after certainty that the Iranian government would unilaterally terminate the contract themselves, following the 1979 Iranian Revolution, which led to a crisis in Iran's relations with the West. Shortly afterwards, Iraq invaded Iran and the nuclear program was stopped until the end of the war.
In 1984, Kraftwerk Union did a preliminary assessment to see if it could resume work on the project, but declined to do so while the Iran–Iraq War continued. In April of that year, the U.S. State Department said, "We believe it would take at least two to three years to complete construction of the reactors at Bushehr." The spokesperson also said that the light water power reactors at Bushehr "are not particularly well-suited for a weapons program." The spokesman went on to say, "In addition, we have no evidence of Iranian construction of other facilities that would be necessary to separate plutonium from spent reactor fuel."[citation needed] The reactors were then damaged by multiple Iraqi air strikes from 1984 to 1988, during the Iran–Iraq War.




Continuation of work by Russia's Atomstroyexport




In 1990, Iran began to look outwards towards partners for its nuclear program; however, due to a radically different political climate and punitive U.S. economic sanctions, few candidates existed.
A Russian–Iranian intergovernmental outline construction and operation agreement for building two reactor units at Bushehr was signed on 25 August 1992. Two years later, Russian specialists toured the site for the first time to assess the damage done to the partially complete plant by the passage of time and by air raids during the Iran–Iraq War. The final contract between Iran and Russia's Ministry for Atomic Energy (Minatom) was signed on 8 January 1995. Russia's main contractor for the project, Atomstroyexport, would install a V-320 915 MWe VVER-1000 pressurized water reactor into the existing Bushehr I building, with commissioning originally expected in 2001.




Difficulties




After the dissolution of the Soviet Union, the Russian government ended its subsidies to contractors building power plants for foreign customers, putting Atomstroyexport in financial difficulties. Another obstacle was the shortage of Russian engineers and technicians with suitable experience. The last nuclear plant built in the Soviet Union was the No. 6 reactor at Zaporizhzhya in Ukraine, which is why Ukrainian specialists were invited to work in Iran after they had finished the work at Zaporizhzhya.
The 1995 contract with Iran stipulated that a share of construction and installation jobs would be reserved for Iranian subcontractors. These companies were inexperienced and had been only minimally involved in the German project, which resulted in their 12-month work being delayed over 3-years (1995–1997). Due to these difficulties, in 1998 Minatom pushed through an agreement that Atomstroyexport would finish the first reactor on its own. The agreement was signed on 29 August 1998 as an addendum to the main contract.
The extremely hot and humid climate of the Bushehr area, with lots of brine in the air due to the proximity of the ocean, represented a special challenge for the construction. In such conditions, even stainless steel can rust, and a special painting technology had to be developed to protect the station's structural elements. In the summer the temperatures can reach 50 °C (122 °F). While the German companies worked at the site, the workers had a special clause in their contracts to allow them to stop working during the summer heat waves.
German engineers had left behind a total of 80,000 pieces of equipment and structural elements, with little technical documentation. The Iranian side insisted that the German hardware must be integrated in the Russian VVER-1000 design. Germany refused to help in the construction, mostly for political reasons, as Iran was under an embargo for nuclear plant components. Therefore, it was decided to take stock of the existing equipment using only Russian expertise.
The 1998 addendum to the construction contract put the final value of the project at just over $1 billion. Since then, the sum was never adjusted for inflation, resulting in funding shortages.




Revised contract


In response to American and European pressure on Russia, a new revised agreement was reached in September 2006, under which fuel deliveries to Bushehr were scheduled to start in March 2007 and the plant was due to come on stream in September 2007 after years of delays. In February 2007, the work on the site started to grind to a halt due to funding shortages, and Atomstroyexport reduced the number of employees working on the site from 3,000 to just 800. During subsequent negotiations, Atomstroyexport even contemplated pulling out of the project. In the end, an agreement was reached, under which the Iranians would compensate for the growing cost of equipment and engineering works once the reactor would go live. A top Iranian nuclear official claimed that the Russians were deliberately delaying and politicising the project under European and American pressure.
Prior to the contract revision, the price was about a third that of a contemporary reactor, at just over $1 billion, reflecting the year of the original contract and that it was the first post-Soviet nuclear export order. Increased material costs and currency fluctuations had made completion at that price difficult.
According to Moscow Defense Brief, until 2005 Washington exerted considerable diplomatic pressure on Russia to stop the project, as the US administrations viewed it as evidence of Russia's indirect support for the alleged Iranian nuclear arms program. The United States also tried to get other countries to ban their companies from taking part. For example, Ukraine's Turboatom was to supply a turbine, but cancelled the deal after the US Secretary of State Madeleine Albright's visit to Kiev on 6 March 1998. The United States lifted its opposition to the project in 2005, partly due to the deal signed by Moscow and Tehran, under which spent fuel from the plant would be sent back to Russia.




Finishing the plant


In 2007, according to Moscow Defense Brief, Russia made a strategic decision to finish the plant, and in December 2007 started to deliver nuclear fuel to the site. On 20 January 2008 a fourth Russian shipment of nuclear fuel arrived. Russia has pledged to sell 85-tons of nuclear fuel to the plant.
In March 2009, the head of Russia's state nuclear power corporation Rosatom, Sergei Kiriyenko, announced that Russia had completed the construction of the plant. A series of pre-launch tests were conducted after the announcement.
On 22 September 2009, it was reported that the first reactor was 96% complete and final testing would begin in the near future. In early October final testing was started.[18] In January 2010, Kiriyenko announced to the public that the Bushehr reactor would be opening in the near-future, declaring 2010 the "year of Bushehr."




August 2010 fuel loading


On 13 August 2010, Russia announced that fuel would be loaded into the plant beginning on 21 August, which would mark the beginning of the plant being considered a nuclear facility. Within six months after the fuel loading, the plant was planned to be fully operational.
An official launch ceremony was held on 21 August 2010 as Iran began loading the plant with fuel. At the ceremony, Iranian nuclear chief Alki Akbar Salahei said:
"Despite all pressure, sanctions and hardships imposed by western nations, we are now witnessing the startup of the largest symbol of Iran's peaceful nuclear activities."
Although they have opposed the project in the past, Western governments now stress that they have no objection to the demonstrably peaceful aspects of Iran's nuclear programme such as Bushehr, according to the BBC. Spokesman of the United States State Department, Darby Holladay, stated that the United States believes the reactor is designed to produce civilian nuclear power and does not view it as a proliferation risk.
On November 27, 2010 the head of the Atomic Energy Organization of Iran declared that "All fuel assemblies have been loaded into the core of the reactor" and they were hoping that the facility "will hook up with the national grid in one or two months".
The plant is to be operated by Russian specialists. Russia also provides the nuclear fuel for the plant, and spent fuel is sent back to Russia. Once online, the Bushehr plant will satisfy about 2% of Iran's projected electricity consumption.
The former head of Pakistan's Inter-Services Intelligence hailed Iran's launch as a positive move in the Muslim world, and he also said that an anti-Iran campaigns by the US and Israel stems from Iran's Islamic status. "Bushehr Nuclear Power Plant is a victory for Iran and indicates that Iranians do their best to achieve their peaceful objectives but the US and Israel are not ready to accept this achievement."




May 2011 sustained nuclear reaction


In February 2011, Rosatom announced that one of the reactor’s four main cooling pumps, from the original German reactor, had suffered damage. Thoroughly cleaning the reactor of metal particles required the removal of the fuel core, resulting in a startup delay. The reactor achieved a sustained nuclear reaction at 11:12 on 8 May 2011 and ran at a minimum power level for final commissioning tests.




September 2011 official launch


The plant started adding electricity to the national grid on 3 September 2011, and the official inauguration was held on 12 September. By the inauguration time the plant operated at 40% capacity, while the full projected capacity of the first unit is 1,000 megawatts The opening ceremony was attended by Energy Minister of Russia Sergei Shmatko and head of the Russian Federal Atomic Energy Agency (Rosatom) Sergei Kiriyenko, AEOI Director Fereydoun Abbasi, Iranian Energy Minister Majid Namjou, and a number of Iranian MPs.
Under the terms of Russia–Iran agreement, approved by the International Atomic Energy Agency, Russia will be responsible for operating the plant, supplying the nuclear fuel and managing the spent fuel for the next two or three years before passing full control to Iran.[4] Before the plant will reach full capacity in November, it will be disconnected from the grid for several weeks to make a number of tests.




Russian–Iranian relations


The total cost of the project is estimated to be over €3 billion including the payments to both Russia and Germany. The original 1995 contract with the 1998 addendum was worth $1 billion and was not adjusted for inflation. Although in 2007 Iran agreed to compensate for the rising costs after the construction is finished, it is regarded that the possibility of the project turning a profit are remote. However, the project allowed the nuclear industry of Russia to preserve its expertise in times when funding was scarce, and until the sector started to receive orders from China and India.
According to Moscow Defense Brief, completion of the plant could become an indicator of Russia's credibility in large international high technology projects, and the successful integration of German and Russian technology could help the Russian nuclear industry in its ambitions to partner with foreign companies in building nuclear power plants in Russia and abroad.
Since Bushehr's nuclear reactor has been under construction by different firms and consultants, the constituent parts have also different origins. 24% of the parts are German in origin, 36% are Iranian made while 40% are Russian made parts.
Tehran and Moscow have established a joint venture to operate Bushehr because Iran has not yet had enough experience in maintaining such installations. However, Iran may begin almost all operational control of the reactor within two or three years.
A further two reactors of the same type are planned. The fourth unit was canceled.

No comments: