Mortenson Construction has declared the wind energy industry “challenging and uncertain” after developing 100 wind farms in the United States and Canada.
The
assessment by Mortenson, based in Golden Valley, is in its new 20-page
report titled “Facing the Wind” (available at mortenson.com), which
cites difficulty negotiating power purchase agreements, a lack of a
federal renewable energy standard and undeveloped transmission lines as
key issues. Thirty wind energy project owners or developers gave
feedback for the report.
Minnesota
is ranked No. 7 nationwide in wind energy capacity, with 1,818
megawatts of construction - or the equivalent of 1,212 General Electric
1.5-megawatt turbines.
As
of Sept. 30, Minnesota listed 677 megawatts of wind farms under
construction - far better than the zero listed by No. 2 wind energy
state Iowa.
And
there is plenty of real estate left to develop in the windy segments of
Minnesota, which form an “L” spanning the state’s borders with Iowa,
North Dakota and South Dakota.
Minnesota’s
under-construction figure is far higher than in early 2010, when
protesters delayed construction of Goodhue Wind, a 78-megawatt wind farm
near Red Wing.
That development appears headed for a lengthy contested hearing process in 2011.
In
the meantime, “I think challenging and uncertain are good words,” Peter
Mastic, president and chief executive of Minneapolis-based National
Wind, said of Mortenson’s characterization. National Wind is behind the
Goodhue project.
The
report describes problems including financing, assessing the long-term
competitiveness of wind energy, finding locations and dealing with
complaints from neighbors as inhibiting development of wind farms.
“I’m
less worried about the long-term competitiveness of wind,” Mastic said.
“The thing that many people forget is that once you commit to a wind
project there is very little cost. If you look at the full life-cycle
cost of wind farm versus the full life-cycle cost of a natural gas
plant, wind is very competitive.”
The
low price of natural gas, which led several Minnesota utilities to
refurbish old coal-fired power plants to cleaner-burning natural gas,
was cited by 70 percent of respondents as diminishing the growth of
renewable energy. An additional 9 percent said natural gas will have a
“significant impact” on the development of renewable energy.
One
key inhibitor to building new projects mentioned in the Mortenson
survey - the lack of a federal renewable energy standard, or RES - could
give evidence to developers and banks financing renewable energy
projects that the industry is viable.
In
2007, Minnesota lawmakers passed RES legislation that required electric
utilities to generate 25 percent of their electricity from renewable
resources by 2025. Xcel Energy, the state’s largest utility, must
generate 30 percent of its power from renewable sources by 2020 under
that law.
A
Jan. 7 compliance report issued by the Minnesota Office of Energy
Security said Xcel Energy has sufficient renewable generation or
renewable energy credits to meet the 2010 requirement of 15 percent
renewable energy.
Other
state utilities will not need to file until the end of 2012, when they
are required to generate 12 percent of their power from renewable energy
sources.
According
to the American Wind Energy Association, the amount of wind energy
installed nationwide plunged 71 percent in the first nine months of
2010, compared with the same period in 2009.
Even so, conditions seem to be improving.
One
key factor was the $18 billion, one-year extension of tax credits for
renewable energy projects passed Dec. 17 by Congress. That vote gave
industry executives until the end of 2011 to finish projects and receive
a 30 percent investment tax credit.
“It’s
been a very challenged industry, but there are some indications that
things might get a little bit better,” said Jeff Wright, the former
president of Minneapolis-based Midwest Wind Energy Finance.
Wright,
principal and founder of GreenWright Partners, a Minneapolis renewable
energy consultancy, expects that financing and development of energy
projects should be by-products of increased demand for electricity since
the recession.
Cameron
Snyder, a spokesman for Mortenson Construction, said his company
maintains a sense of optimism despite a lackluster 2010.
“Our business is growing,” said Snyder, noting that Mortenson plans to open a new office in Toronto on Jan. 19.
Unknowns
at this time are the long-term impact of groups objecting to wind
farms. Those groups have focused primarily on the effects of
low-frequency noise, shadow flicker from spinning turbine blades and
electric emissions related in underground wiring.
No comments:
Post a Comment